Project Overview
The purpose of this project was to construct 23 Bus Boarders within Cardiff City Centre on Cathedral Road and Dumballs Road. These are the main thoroughfare for traffic accessing the nearby city centre.
Scope of Works
Traffic management
Breaking out of existing concrete footpaths (70-90mm)
Laying of new Kassell kerbs and edgings
Surfacing, road markings and site signage
Lifting and storing for re-use block paving
Pipe laying/gulleys (minor excavations)
Re-laying of manhole covers
Liaising with statutory authorities
Implementing environmental strategies
Day to day dealings with the general public
Carriageway reinstatement
Logistics strategies for delivering materials